2023/2024 Pavement Management Program
2023/2024 Pavement Management Program
Information is updated as it becomes available. We strive to provide 3-5 days advance notice for abutters to a road reconstruction project, however there are occasions when contractor availability or unforeseen conditions delay or accelerate the schedule. When this occurs we make every effort to notify residents as soon as possible.
All projected dates are subject to change and are weather permitting.
STREET | FROM | TO |
CHESTER RD | OAKLEY RD | COMMON ST |
HAMMOND RD | PALFREY RD | GILBERT RD |
FLETCHER RD | TYLER RD | CLIFTON RD |
WASHINGTON ST | COMMON ST | GODEN ST |
BRIGHT RD (SB Lane) | WASHINGTON ST | CONCORD AVE |
MILL ST | STANLEY RD | 300' N OF TRAPELO RD |
- BID OPENING 9/8/2023
- NOTICE TO PROCEED 9/28/2023
- SEWER ESTIMATED START DATE 12/11/2023
- ROADWAY ESTIMATED START DATE 5/1/2024
STREET | SEWER/DRAIN START | SEWER/DRAIN END |
CHESTER RD | 12/19/23 | 12/21/23 |
HAMMOND RD | 12/12/23 | 12/15/23 |
FLETCHER RD | 1/2/24 | 1/5/24 |
WASHINGTON ST | 12/20/23 | 12/21/23 |
BRIGHT RD (SB Lane) | 1/29/24 | |
MILL ST | 12/28/23 | 1/9/24 |
ROAD CONSTRUCTION
STREET | LOWER UTILITY STRUCTURES | RECLAM- ATION | ASPHAULT BINDER | ACCESS- IBLE RAMPS | DRIVEWAY APRON | SIDEWALK | FINAL PAVING |
CHESTER RD | 4/8/24-4/9/24 | 4/29/24-5/3/24 | 5/3/24 | 5/14/24 | 5/14 | 5/14 | |
HAMMOND RD | 4/9/24 | 4/29/24-5/3/24 | 5/3/24 | 5/13/24 | 5/13 | 5/13 | |
FLETCHER RD | |||||||
WASHINGTON ST | |||||||
BRIGHT RD (SB Lane) | 5/28/24 | 5/29/24 | 5/29/24 | ||||
MILL ST |